Work on Selly Oak New Road begins

posted by James Thornett
Following my post last month on the proposals for the Selly Oak New Road it would appear that, as promised, work has now begun.

This from birmingham.gov, updated on 25th October:

Phase 1A of the scheme includes for the widening of Harborne Lane, reconstruction of Harborne Lane bridge, the construction of a new roundabout at Harborne Lane / Selly Oak New Road, construction of new carriageway across the old Birmingham Battery site and flood compensation works.

The following works are due to take place from Monday 29 October:

  • Importing and rolling fill
  • Drainage works
  • Trial holes in footpaths

Please note that the location of these works means traffic flows will not be affected

If you need further information please contact either George Underhill on 07977 437305 or Dave Greenaway on 07766 923287.