Another brief update from birmingham.gov on the progress of the Selly Oak New Road:
The following works are due to take place from Monday 4 February 2008:
  • Importing and rolling fill material for new road and roundabout.
  • Work on north wing wall for the first section of new canal bridge, Harborne Lane.
  • Waterproofing, back of wall drainage and backfilling to back of walls.
  • Placing gully connections.
  • Site clearance and excavation to east pavement will be taking place.
  • Work on retaining wall next to B&Q.
  • Excavating lagoon and stockpiling arisings.
  • Tree clearance to the environmental works off Arosa Drive

Both carriageways are restricted to one lane working, which may cause disruption for motorists and pedestrians.

If you need further information please contact either George Underhill on 07977 437305 or Dave Greenaway on 07766 923287.